Can a site stop conserving solution gas if production falls below 900 m3/d?

Category:

Flaring and Venting

Research Basis

Archive Period

1999-2025

Records Reviewed
33
Primary Topics
discontinue conservation; solution gas; approval; 900 m3/d; AER application
Current Reference
AER Directive 060; Bulletin 2026-12

Common Question

Can a site stop conserving solution gas if production falls below 900 m3/d?

Archive Findings

No. The archive showshistorical records indicates that prior conservation is the trigger, not only current volume.

Historical records indicate that if a site was previously conserving, approval to discontinue solution gas conservation was required regardless of volume.

Engineering Insight
ChatGPT Image Jul 11, 2026, 04_05_45 PM (2).png
Need help with an application?

Our team can help you navigate regulatory requirements, prepare strong applications and avoid costly delays

587.880.2249

Check conservation history before giving a flaring answer. If the gas was previously conserved, prepare a discontinue-conservation request instead of relying only on the 900 m3/d threshold.

Current Guidance

Current Directive 060 requires an AER request to discontinue conservation once conservation has been implemented, including where produced volumes have dropped below 900 m3/d.

Related Regulatory Insights

Historical newsletter insights that reference the same directive, manual, rule or regulatory requirement.

May 1, 2025

Benoit+ WellFile and Key 2025 Directive Updates

This issue introduces Benoit+ WellFile and summarizes regulatory updates involving Directive 040, Directive 060, Directive 039, Directive 020, pilot-technology guidance, shallow-rights reversion, Saskatchewan orphan matters, and BC EIMS items.

Mar 1, 2025

Facility Life-Cycle Status Validation and 2025 Levy Updates

This issue focuses on facility life-cycle status validation, OneStop land updates, 2025/26 levy information, Directive 060 matters, wildfire-related updates, and BC facility-streamlining changes.

Sep 1, 2020

Directive 060, Commingled Abandonments and Well Testing Updates

This newsletter covers Directive 060 updates, well testing, Saskatchewan commingled-abandonment guidance, step-rate injectivity test interpretation, Saskatchewan groundwater-protection GIS, BC pressure-isolation-test submission changes, and well-spacing education.

Mar 1, 2018

Directive 060, OneStop Drilling Data and Subsurface Orders

This issue covers Directive 060, Directive 059 well drilling and completion data in OneStop, Saskatchewan acid gas disposal, geothermal and CO2 IRIS items, subsurface orders, and LMR/IWCP content.

bottom of page