top of page

Regulatory Intelligence 

Does a pipeline licence application cover pipeline-installation work?

Category:

Pipelines

Research Basis

Archive Period

2015-2025

Records Reviewed
71
Primary Topics
D056; pipeline licence; pipeline installation; pipeline amendment; resumption; Manual 012
Current Reference
AER Directive 056; AER Manual 012

Common Question

Does a pipeline licence application cover pipeline-installation work?

Archive Findings

In 2025 correspondence, AER answered that the pipeline-installation items were not included in the pipeline licence application. The folder also separates pipeline installations, licence amendments, resumption, MOP increases, substance changes, liners, and composite installations.

One physical project can require more than one regulatory filing.

Engineering Insight
Need help with an application?

Our team can help you navigate regulatory requirements, prepare strong applications and avoid costly delays

587.880.2249

Break the project into regulatory objects before filing: pipeline, installation, facility, amendment, resumption, pressure change, or substance change. Map each object to its filing requirement.

Current Guidance

Use Directive 056 and Manual 012 to confirm pipeline licence, pipeline installation, amendment, and resumption filing requirements.